How can a Developer Estimate Times?
Posted by
Cliff
on Sat Jul 01, 2006 10:30 PM
from the estimates-pulled-from-hats dept.
from the estimates-pulled-from-hats dept.
SubliminalVortex wonders: "Many times in the past, I have been asked on 'how long' it would take to implement a certain features/fixes in a product. What's interesting is that many times, certain 'fixes' is adjusting the wording/placement of the items in question; in other cases, users want the product to do everything they ever imagined, since it already started by following their line of thought. From there, the problem continues. From the user interface, people 'imagine' and think that 'oh, it would be easy if...' and scenarios occur, not only internally from the company using the product, but the clients themselves. Usually, several good ideas are there, but estimating times is a pain in the arse if you have a platform you're writing code for which has no documentation. How do coders estimate times to their bosses? If I know the answer outright, I'll give it, but in some cases, I don't how much time I'll take from other developers *because of the lack of documentation*. I'm going to have to bring in my D&D dice next week just to start."
This discussion has been archived.
No new comments can be posted.
The Fine Print: The following comments are owned by whoever posted them. We are not responsible for them in any way.
Full
Abbreviated
Hidden
Loading... please wait.
Design the feature out (Score:5, Insightful)
Re:Design the feature out (Score:3, Insightful)
Re:Design the feature out (Score:3, Insightful)
Just try to be fair in your estimate; fair for yo
Re:Design the feature out (Score:4, Insightful)
As for comparing time- first, you have prior experience. Having done something similar on another project can give you a good idea as to time. Then there's similar things to another part of the program. Finally, just because something is similar doesn't mean the code can be shared. But it does give you a yardstick for time.
Parent
Re:Design the feature out (Score:3, Interesting)
Re:Design the feature out (Score:5, Insightful)
Newbie : 8x as long as estimated.
Seasoned Developer : 3x as long.
Elite Veteran : 2x as long.
Here's the rule I use when dealing with developer estimates (copied from a post almost a year ago) :
Time estimage guidelines:
New programmer fresh out of college: Take his estimate and multiply by 8x. Yes he could get it done in 1 day, assuming he got so cranked up on caffeine his eyes stopped blinking and he worked on that (and nothing else) for 24 hours straight. In the real world a newbie can dedicate about 2 real hours doing a particular task each day, the rest is spent coming up to speed on corporate coding standards and libraries, email, breaks, and not 'in the groove'. Also, you are expecting him to document it but he didn't account for that in his estimate - his estimate was only for time to code the actual lines of code.
Veteran programmer of average skill, single person project : multiply his estimate by 3x. A third of his day is spent hand-holding the newbie, and another third is spent hand-holding management. The other third is spent programming, but luckily he knows to pad the schedule some (not enough, but some.)
Veteran programmer of uber skill, single person project : multiply his estimate by 2x. This is as good as it gets. A uber veteran programmer knows to leave his email client closed and his door closed so he can stay in the zone. He knows to pad the schedule more than he really thinks he should. And it still takes him twice as long as he expected.
Multiple people working on the same project : increase the timeline by a factor of 1.2 per additional person. If two people ought to be able to do it in 10 days it will take 12. If 11 people (10 additional) ought to be able to do it in 10 days it will take
Parent
Re:Design the feature out (Score:3, Insightful)
Ah, yes. Stealth requirements. The seasoned developer will be familiar with the practice of requirements which you didn't mention, and when asked about them, will say, "Well, that goes without saying!". And it's true, it *did* go without your saying it...
Dilbert always has the answer (Score:2)
http://lazybastard.ehuna.org/archives/000032.html [ehuna.org]
Re:Management Solution (Score:3, Funny)
Hahahaha! Good one!
Management also often has information you may not haveHoo-haa! You're on a roll!
he/she isn't likely to be around much longerStop, please, you're killing me!
Use the Estimator's Rule (Score:5, Insightful)
It always takes longer than estimated, even after accounting for the Estimator's Rule.
Scrum Development Process (Score:2)
Re:Scrum Development Process (Score:2)
From what I've seen so far, they just wanna know how far along we are, not how long we think it might take.
Re:Scrum Development Process (Score:3, Interesting)
Yes, but it's better to know in two days that your estimate is wrong than wait thirty days. Also, a lot of SCRUM is breaking things down to an understandable level. I.e. down to problems like, "Design the initial schema for the main database table" rather than problems like "Define the database schema for the project." It's much easier to determine how long it will tak
Re:Scrum Development Process (Score:3, Insightful)
Do not confuse complexity with unknowability. A sulfuric acid manufacturing plant is complex, but every part of the process is known, and is known to be repeatable; and thus it is reasonable to ask how long it will take to build a proposed sulfuric acid manufacturing plant and how much it will cost.
Scrum is a development method for nontrivial software projects with many unknowns and little repeatability.
Re:Scrum Development Process (Score:3, Informative)
The Scrum process requires meaningful-to-stakeholder progress every 30 days, not every 24 hours. The 30
Re:Scrum Development Process (Score:3, Interesting)
I'm still leery of the distorting effect of reporting, though. If a manager's credibility or ability to act is negatively affected by hi
how to estimate development times... (Score:2, Funny)
More seriously, I've found from past exeperience you should always take whatever time you think the project will take and multiply that number by 2 or 3. If you are lucky (and the customer requirements don't change to much) you should make it.
Re:how to estimate development times... (Score:2)
dartboard.
Take whatever time you think it will take and multiply by the number you throw. Cahnces are, you'll still be too low ...
Experience (Score:5, Insightful)
Re:Experience (Score:2)
To break it down sufficiently will mean you'll be doing all the developing except the actual code and testing.
Who's paying for that?
I have to ask... (Score:2)
Good 'ol Scotty (Score:5, Funny)
Win-win.
Re:Good 'ol Scotty (Score:3, Insightful)
I think you left something off at the end. "And if you get it done early, you will be rewarded with even less time for the next project."
Manager theory (Score:5, Funny)
Double your realistic estimate for each DM.
Re:Manager theory (Score:3, Funny)
No Easy Answers (Score:2, Interesting)
The best approach I've found is to decompose the problem into chunks that are small enough to give a reasonable estimate of, but I've hit two snags with this:
1. it may take time I don't have to do the decomposition
2. managers don't like big numbers
Good luck!
Re:No Easy Answers (Score:4, Insightful)
I would add, dont let them sucker you into making
an estimate without doing the decomposition, if there
are items that are risky because it is something
newish, allow time ( up front is best ) to do some
empirical development to figure out how it all works,
and if you normally pad estimates with a x 2 factor,
pad this part with a x10 factor.
*Dont* succumb to the temptation to cut back any
estimates once you see what the totals come out
to. Do your estimation at the "leaf nodes" only, and
let the numbers come out as they come out.
And even if the managers dont like the big numbers,
at least *you* will know. They may well tell you you
have less time than you asked for. Dont agree when
they come out with the "it wont *really* take that
long, will it?" stuff. Stand your ground, but realize
you may not get the time. Then you can pre-prioritize
how you execute on the project, so that the most important
stuff is done ( hopefully ) when their stupid deadline
comes up. Now, that does not mean that you should be
disagreeable in your disagreement. But when they
throw on the pressure to bring forward the deadline,
find a way to remind them that you are working toward
that deadline, but you dont think it achievable. Course,
then they will try the "we cant have you lead unless you
buy into our stupidity" kind of stuff. Dont have
an answer to that.
Parent
It just takes experience (Score:2, Informative)
How I go about making this initial guess is by breaking the pr
Experience, solid requirements (Score:5, Insightful)
For the most part, your ability to give an estimate on a change is a matter of experience. General experience will give you a rough idea of how long it would take to implement some random feature. Specific experience with the system in question will give you a much more refined ability to make an estimate. If you can't make an estimate, or you can only make a rough estimate, be upfront about it. Tell your manager or the customer (if you're the one working directly with the customer) that your estimate is very rough, and try to add as much buffer time as possible. Also, don't get into granular estimates when you can only give a rough SWAG (Some Wild-Ass Guess). If you think it'll take you an hour, say a day. If you think it'll take you a day, say three. If you think it'll take you three days, say a week (experience will tell you how much buffer to add). If you don't have enough experience with the system to make a good estimate, ask your co-workers for help. It's always better to under-promise and over-deliver than the other way around. Besides, while you may end up over-estimating some feature, chances are you also underestimated another one and the extra buffer time you don't need for feature A will be invaluable to finishing feature B.
To help you make better estimates, you should make sure you get a solid set of requirements from your customers. Time should be spent with the customer to determine exactly what it is they want (they may not be able to articulate it clearly), and whether or not there's already a solution they could use if they're only willing to change their process. Avoid telling the customer at that point whether something is "easy" or "hard" (and definitely ignore them when they suggest something will be easy -- they don't know the inner workings of the code, so how will they know if it's hard or easy? Changing a piece of text may look trivial, but may involve a number of external factors such as localization or legal that would turn a 5 minute fix into a two month battle). Take what you've learned, distill it down into a solid set of requirements, and take that back to the customer for sign-off. Once they've signed off, they don't get to change their mind any more for this cycle (however long that may be -- days, weeks, months, or even years, though hopefully not nearly as long as that). Then you get rough estimates from the developers based on their gut feelings and knowledge of the code base, and have them investigate deeper to solidify those estimates. At that point, you have enough to build a schedule, but allow for buffer time! A developer's 8 hour day may not be 8 full hours of coding. It may be 4 hours of coding, two hours of meetings, an hour for lunch, and an hour of "filler" for the cost of task-switching depending on how the coding hours and meeting hours overlap. Based on your experience with past projects, you should have a good idea of how much time per day a dev actually gets to spend on coding and use that to build your schedule. For example, developer estimates are all in 8 hour day increments, but you know from experience that developers average 6 hours per day of productive work. That means a 5 estimated days will actually take 6.7 real days, so use that as your buffering criteria. (BTW, six hours of productive work is actually high. In most cases, it's really closer to 4 or 5.)
Finally, don't forget QA. Just because a developer has confidence that he can implement a specific feature in one hour doesn't mean it won't take QA a week to verify all of the ramifications of that change. You really need to have your QA team working in lock-step with your dev team. Your dev team should write technical specs on the features, and your QA team should estimate impact off of those. The "agile" disciplines that are en vogue lately try to incorporate testing directly into the development process, which is good. However, that means that developers will be in charge of including QA costs on their estimates, which developers are usually bad about doing
My one-time mentor taught me well (Score:2, Interesting)
One hour becomes two days. A week is two months. A month is two years.
P.H.: If you are reading this I'm still in the business.
Be Honest (Score:5, Informative)
Qualify Your Answer (Score:2)
How to arrive at your estimate (Score:2)
Multiply by 250%
Add at LEAST two weeks on top of that.
Tell your (un)friendly PHB "the schedule is NOT negotiable (for acceptable quality) unless they start cutting back features, oh and as a friendly reminder, PHB, throwing more programmers into the mix this late in the game will NOT speed things up, and outsourcing it whole or in part to India c
Confidence Intervals (Score:2)
Draw a line through the min column. Min column is just for amusement. Total the max column and then double it.
If you feel like you need more fudge
I'm a fan of the WAG method (Score:2, Informative)
yer gonna have to spec it out... (Score:3, Insightful)
A nice article by Joel Spolsky (Score:3, Interesting)
This might help: Painless Software Schedules [joelonsoftware.com].
Steps that help (Score:3, Insightful)
o Break the problem down into small pieces. If you have an item on your schedule that says "Do X" and the estimate is "two weeks", you do not understand what X is. Keep splitting it into X.1, then X.1a, then X.1a.ii, until the pieces are all less than three days, preferably much less.
o Clock time != development time. You will spend half your time going to meetings, preparing TPS reports, and making phone calls to find out why your test server is down. To convert development hours to schedule hours, use a factor of two.
o Keep an estimator's handbook. Ever noticed these in a technical bookstore? You can look up how long it takes to plumb a bathroom, build a wood frame wall, etc. Keep your own list of how long it takes to build a credit card form or a bulletin board. Look up the phrase "function point" in ancient literature and see if you get any useful ideas.
Ah, time estimation (Score:5, Insightful)
Time estimation is part of project managment. A good course in project management will give you the tools to effectively deal with these situations.
Short and sweet, when asked to give an estimate (any estimate) ask them if they want the quick and dirty estimate now (which may be off by 1,000% or more) or if they would like a more accurate estimate. If they want the quick and dirty then use whatever method you use now to give them the estimate. If they want an accurate estimate then tell them you'll research the current state of the project, the development effort required for functions x, y, and z, and the resources required to accomplish the effort.
Then follow a good estimating process - there are many available in many books about this subject. In my case generally new projects are very similar to older projects, and are all built on the same foundations so it's easy to start with a list of tasks to get from point A to B, and list the resources and dependencies for each task. Link them all together, and then go to the boss and say, "Assuming that we have these people and these reources, the project will be completed x weeks from kick-off."
When (not if) the boss says, "Well it needs to be done by this date!" Calmy reply with, "We can meet that goal by either scaling the work back, or increasing manpower. Which is more suitable for this situation?" and so on.
The one thing you don't want to do (that all too many software engineers do on a regular basis) is over estimate or underestimate the work required. In either case the customer (generally your boss) learns not to trust your estimates. This is bad on so many levels, and is the main reason that so many software engineers work more than 40 hours per week on a regular basis - especially those that overestimate the time required trying to combat this (paradoxically).
A more accurate estimation process will include a frank discussion of risk and risk management. "This schedule is good as long as we assume the code base is well documented and follows reasonable coding practises." Then find out what the customer wants you to do if you find this assumption to be false. Give them the whole scenario - the risk may be low, but if the assumption proves wrong then perhaps the project schedule or resources just tripled. That may be too great a risk to take even if it's unlikely - so how do we mitigate that risk?
I could go on, but really this is a basic question that millions of people have asked for thousands of years. There are much better and more thorough resources to answer it. Visit your local library if your company isn't willing to send you to a simple three day project management seminar. They won't teach you much that's new, but they'll tie it all together and give you the tools you need to communicate effectively with others - most of the important stuff is being able to say, "I'll get back to you on that by thursday."
-Adam
DON'T DO IT! (Score:5, Insightful)
Don't do it!
I'm serious. If we've learned anything over the past forty years, it's that trying to estimate software development time is a waste of time. Why? Well, for one things, bugs. To know how long it would take to find and fix them, you'd have to know what the problem was, which means the hard part's done. For another thing, specification flux. Most reasonable project specifications for non-trivial projects don't provide enough information to accurately predict how long it will take to code. And producing such specs, and using them, will take longer than the development would have taken in the first place. And, if that's not enough, think of Dilbert. Specifically, the one where his boss asks him "Will there be any unforeseen problems?"
I once told a client (a dot com) "I'll tell you how long this will take if you can tell me what you stock will be worth six months from now, four months after you IPO. And I'll be more accurate than you will. If you'd rather, you can tell me when the next two-day rainstorm will be." He hemmed and hawed, and basically refused to give any sort of number whatsoever. I said "Good, it looks like we've got a nice honest relationship going here. Neither of us is willing to lie to the other, or claim to know something we don't. So let's start prioritizing these features for the mock up."
Let me say it again: Don't even attempt to estimate development times.
So what should you do instead? Incremental development with frequent opportunities for feedback. Ideally, the users should be able to play with a nightly-build prototype whenever they want from the first week or so on. If they ask for a time estimate, tell them it will be done when they're happy with the result, and don't want anything more, or they're unhappy with the rate of progress, and call the whole thing off.
But don't lie to them, no matter how hard they push.
--MarkusQ
Partial agreement... (Score:5, Interesting)
The last thing you ever want to do when asked by a manager is give a off the cuff answer. It will almost always be wrong.
So what do I do when I get asked how long something will take? Well, to start off, if I know the code in and out, and I'm aware of the bug, then I can actually estimate what amount of time it will take. If it's not a bug, but something to be developed, and I've done the exact same thing before in my career, I already know the answer.
If however, neither of these are the case (which is about 98% of the time), I say this: "It'll take me roughly x hours to investigate this matter further and only after that will I be able to give you a timeline that is accurate."
First off, that gives you way more credibility, and way more leeway. But second, it lets you dive into the situation without having committed your life to fixing it, until you get a better grip on what's going on. If I were for example dealing with a bug on a web app (the kind I regularly work on these days), I would say something like "It'll take me 4 hours to investigate". I will most likely start with about an hour spent understanding the scope and possibly the history of the bug. "Is it reproducible?" is the most important question. If it is intermittent, I will commit to nothing at this point. If I look at the code and can see what is causing the problem, that is, if I can see a clear cause and effect chain that agrees with the test cases etc, I rely on my prior experience and make a guess at how much code needs changing. Plan for it, and plan conservatively. *DON'T* rewrite the application. Only fix the problem.
If you have time left on your initial x hours, start fixing the problem. See how it goes. Does it look like it's just going to keep on going like this until you fix it, or are you finding your being faced with odd and quirky behaviour left right and center? If you have weird behaviour, beware! If you have undocumented libraries/APIs behaving weirdly, beware! Don't get caught with your pants down. Let your manager know that you are passing some data down to the J2EE/COM/.NET/.Salsa/<NameYourCustomFramework> and that it is not acting as expected.
For actual development, the process is slightly different. Assess what needs to be done exactly in the same way as above (give an initial x hours to investigate). See what actually needs to be done. *DON'T* rewrite the STL library or .NET framework to do it. Choose the quickest cleanest path with the least amount of development time. Look at all your prior experience: have you previously used STL? Do you know it like the back of your palm? Have you only briefly used COM? And have you had issues with it the times you did use it? Keep that in mind. Try to steer the project in your domain of expertise. Put that as a coefficient in your estimation. If you know you have 100 lines or so of code to write using a library that you know in and out, estimate what you think it will take. If you will have to use a library that you're not really familiar with, pad it like crazy. I mean 2-3-4 times what you expect.
Those are the practical comments, there's also the more theoretical stuff:
Don't confuse accuracy and precision. And don't let your managers confuse the two. If I am asked to guestimate a project timeline, saying "4 months, 3 weeks, 2 days, 5 hours, 23 minutes" is more precise but radically less accurate than "4 months". Yeah, it sounds stupid, but accuracy != precision. Don't forget that. Tattoo it on your hand if you must. The longer a duration, the less precise it should be. Commiting to February 5th is ok if you are in January, it is not ok if you are in August. If you are in august, you must commit to a month coming up, and warn your managers to give it leeway. Just cause you said "it'll be done in february", doesn't mean they should plan a launch on February 18th.
The other thing is a little concept that I really like in comp sci algorithmics: divide and conqu
Parent
Re:DON'T DO IT! (Score:5, Insightful)
You are completely missing the point here. It is precisely because it is important that you should not fall into the trap of lying to people. Instead, you should do what any other responsible R&D team would do--decouple the processes of R, D, and whatever comes after.
Here's how it works:
The point is, because it's important, don't let it become an all or nothing proposition. Make sure that, on whatever date they need to, they have something to run with, and it is as close as you can come to the best possible version that could be produced by that date.
And it will likely be better than it otherwise would have been, because you can apply all the time you would have wasted defining and defending schedules to actually keep the project moving forwards.
--MarkusQ
Parent
The Personal Software Process (Score:3, Informative)
Dependent variables... (Score:3, Insightful)
http://www.goldratt.com/ [goldratt.com]
There are two keys to delivering almost always on time; Planning and Management.
Planning means thinking the project through in the best detail before you start coding. Agile programming seems to work in short, quick-and-dirty projects, but my experience is that it falls short if the project is large and complex. The less decisons you have to make in the middle of the project, and the less changes you have to make as a result, means that the work can me seen to progress along the planned path.
Management means controlling the variables, and that's where the techniques in "Critical Chain" shine. Nothing, absolutely nothing, is allowed to delay the critical chain in the plan. The biggest dividends come from two parctices: Continuity and Resource management.
It used to be that if I had a week to do a job that I knew I could do in a day or two, I'd do whatever else needed doing and start two days before the task was due. Of course, If something came up, (essential co-worker gets sick, computer crash, virus, software needs updates, whatever) then I might be delayed during that two days and the task is delivered late. If the task was on the critical path, then the whole project becomes late. The first 10% delay on a project typically costs 25% of the profitability, the next 10% late costs 20%, so being only 20% late can cost 45% of the profitability. People tend to think that if they have some slack, they can relax. Then they wonder why they are late. They should work as if there was no slack! Relax at the END, not during.
In a large project with multiple developers, some of them may be required to cordinate along different paths, not just the critical path. This is why Godratta called it the "Critical CHain". Those resources MUST be focussed on keeping the essential workflow from bogging down anywhere that may delay the longest chain of dependencies.
This idea came out years ago, and I've been following project management ever since the 60's. This is the first big change I've seen since 1969. Everyone who told me they tried the Critical Chain method and it didn't work, didn't follow the process. Siemens practically took the whole market for 7200 rpm hard drives by developing them first using the Critical Chain method.
Good luck on your projects.
There never should be a "similar task" (Score:3, Insightful)
But... ever since the days in the 1950s when the subroutine was first invented, there never should be such a thing as a "similar task." Anything that was done before should have been packaged as a subroutine. Or a reusable object. Or a programming system (entire library or language) designed to attack that class of task.
Managers that prize predictability over productivity assign their people to do trivial variations of the same work over and over again and get a predictable straight-line curve of time versus work accomplished.
Good managers allow their people to invest time into tools and techniques are new, hence risky, but pay off with a multiplier effect when they work. They get an unpredictable but exponential progress curve.
(Bad managers, of course, won't accept the notion that a new task should be estimated at the time that a similar task did in the past. They insist that the task should be estimated as if everything were going to go perfectly this time, no missteps, no problems. ("It will take about a year." "Why do you say that?" "Because, remember, the last time we developed the frammis for the foithboinder project, it took a year" "Yes, but a lot of things went wrong. We had several false starts, because the original spec we were given was wrong. And Jim left halfway through the project and it took a while for Kathy up to speed. And we lost a month when we changed over to the new source code control system." "And why do you think nothing will go wrong this time?")
second most difficult question ever (Score:3, Funny)
i just don't devote any more time to these 2 questions anymore...
IT's not documentation that you are missing... (Score:5, Interesting)
It could have been the whole XP process or whatever, but personally I believe it was the testing that allowed us to estimate so well. When something is so well tested, and when you are working from a "test-first" mentality, you get the ability to estimate what you think it will be without having to fudge-factor the results. You do this for a while and you find that your gut instinct gets better and better.
lots of factors are involved (Score:3, Informative)
Creating new code is usually easier to estimate, because once you understand the business rules, you should be able to code it and estimate your time.
Bug fixes, on ANY code ( don't care who wrote it ) can be trickey. It can often be a situation that if you fix one thing your break something else.
There is no real set formula I use, but if I think it will take 3 weeks, I'll say 6. I always double my estimate, and often 'fish' for scope.
Lastly there is nothing wrong with saying 'I'll have to look into that to give you a more accurate estimate. You should be able to take a day or two to get into the code and look at it and figure out enough about it to get an estimate of what is involved. We do this and we call them ballparks. Our ballparks tell how much time the developer needs + qa + spec + IT time + some other things in there. It is usually an estimate.
Then we write a spec, and in the spec we uncover more. Depending on the outcome of the spec and what needs to be added or dropped the bid can change. Also in the spec we identify ALL the programs that need to be changed. These are things that should have been looked at in the ballpark to give you a better idea of what to extimate.
It sounds to me like you are a junior programmer. This has nothing to do with your coding skills and everything to do with your project skills. There are many people who can code circles around me, but they can't always give estimates that are as right on as me. As such, take a look at your code. This should be done in a day no longer. Figure out how much time you think you need to spend on it. Multiply by 3.
After you do this a few times you can start to see how good you are at estimating time. If you estimate time and you are behind on the project, then next time multiply by 4. If you end up ahead of schedule multiply by 2. After a few projects you will be able to say without a doubt exactly how long it will take. Unfortunately some projects will be a range not an exact date, like it will take 6 to 12 months, depending on scope changes.
really though it takes practice to estimate time. Knowing your own skill level, your knowledge of the language and code base, and what other things will always popup, and lastly your interpution level.
I'm sadly the goto guy at my company, so my interruption level is high.
Big or small changes? (Score:4, Informative)
With all but the most trivial changes you need something in writing to confirm what is wanted - even just an email to restate what you talked about and put your estimate in writing. Get in the habit of this. You can talk about it then look at the code for 30minutes and make a far better estimate than being pressuried into giving an answer straight away.
On much larger projects the time spent on actual coding gets less and less and the time spend on specifications, prototypes, testing, documenting, reviewing etc gets much bigger. I recently worked on a $250m sw project where coding was about 20-25% of the time. It depends on what the code is for. Normally coding is about 40% of a project but the more critical a system the less time spent on code and the more spent on design and testing. I've worked on some safety critical systems (ie where someone dies if your code is wrong) and coding was about 10% of the project. This might take a lot of joy out of being a programmer but it pays to get it right!
Old Boss's Forumla (Score:3, Insightful)
He asked each of the software engineers how long it would take, based on their "gut" instincts.
Then he multiplied the figure by two and moved it to the next higher order of time. I.E. weeks become months, months become years. One time he asked us to estimate when we could get something accomplished and we told him two years. He cried for a little bit and went to upper management and said "Never, we can't get that done".
Surprisingly this turned out to be a very effective way for him to gague when things would actually get accomplished, and more often than not he was dead on correct. He also didn't let me in on his secret until just before he quit, but it has also helped me to make my own estimates for customers when I'm doing contract work now. I do the same thing where I make a preliminary estimate based on known issues and then apply the above rule to my own guess. I have (fortunately) been fairly accurate with my guesses at that point, even if it makes the customer angry with them insisting that it must be done in a shorter period of time.